The contract is signed, mobilisation is five weeks away, and the contractor has eight welders on payroll against forty needed. That is how most conversations about welder outsourcing begin — not with strategy, but with a schedule that can no longer move. A client at Tengiz or on a site near Atyrau will not wait while HR digs through databases, and in peak season qualified pipe welders in western Kazakhstan are the first people to be snapped up.
At FSSA we have been filling blue-collar roles on oil, gas and construction projects in the region since 2007, and welding is by far the most temperamental of them. You cannot judge a welder from a CV, a trade grade tells you little about whether a joint will pass radiography, and a bad hire shows up not at the interview but two weeks later, in the QC log. So bringing in welders through an outside provider is not simply "find us some people" — it is an engineering and staffing task in its own right. Here is how it works in practice and where contractors most often lose money.
Welder outsourcing or outstaffing: what are you actually buying?
The industry uses "outsourcing" as an umbrella for any arrangement with external labour, but legally it hides two very different models, and confusing them is expensive.
The first is true outsourcing of welding work. You sign a works contract with a specialist company, and it answers for the result: welded and accepted joints, volume in diameter-inches, deadlines. The provider brings its own procedures, equipment, supervisor and quality control. You pay for output, not for hours. The upside is that the risk of rework and downtime sits with the provider. The downside is that you barely control the process and depend entirely on the provider's technical strength. For isolated packages — tank piping, a section of process pipework — this is often the best option.
The second is staff outsourcing in the narrow sense, or personnel outstaffing — legally, "provision of personnel". Since 2021 it has been regulated directly: Law No. 386-VI of 19 December 2020 added Article 687-1 on the personnel provision contract to the Civil Code and Article 137-1 on the procedure for this activity to the Labour Code. The welders are employed by the provider, which pays wages, withholds taxes and keeps HR records, while you run the work on site: your supervisor, your procedures, your QC. In effect you get people into your own crew without inflating headcount. You can read how we run this service on our staff outsourcing page.
The choice comes down to one question: who owns the welding competence? If you have a strong welding engineer, qualified procedures and your own inspection team, you need hands, and outstaffing delivers them faster and cheaper. If you are the general contractor but welding is not your core skill, it is more honest to hand the whole package to a specialist subcontractor. The worst option, and one we see regularly, is a hybrid with no clear agreement: people are formally "provided", but nobody owns either the procedure or the rework.
One important detail: under personnel provision the law prohibits paying a provided welder less than a permanent employee for the same work. The savings therefore come not from the rate but from flexibility — you do not keep forty people on payroll after the project ends, and you do not spend a month on volume hiring with a two-person HR team.
How a welding crew is assembled for a project
Good recruitment starts with a technical brief, not a job ad. Before looking for anyone, the provider needs to know the materials (carbon steel, stainless, alloy steels), the processes (SMAW, GTAW, FCAW), the diameters and wall thicknesses, and which standard the project qualifies welders to. International projects in the region usually require ASME Section IX, cross-country pipelines API 1104, and ISO 9606-1 also appears. The Kazakh baseline is the Rules for Certification of Welders and Welding Specialists approved by Order No. 468 of the Minister for Emergency Situations of 23 September 2021. If a request just says "grade 5–6 welders" without these details, expect half the candidates to fail your test.
Then comes the funnel, and for welders it looks different from general labour. For forty positions you usually need to invite one and a half to two times as many people to a test weld, and gather several times more applications. The test coupon is the main filter: it is welded on site, in conditions close to real ones, and sent for visual and radiographic inspection. This is where a noticeable share of candidates with perfect paperwork drop out. An experienced welding recruiter asks awkward questions before the test: which sites, what repair rate, which positions you are confident in, have you worked under a foreign client's inspectors.
A typical case from practice: a contractor preparing a turnaround needed twenty-four welders for carbon and stainless steel qualified to ASME. The request read "urgent, grade 5–6". We asked for the procedures and found that a third of the joints were small-bore stainless in awkward positions, TIG. Forty people came to the first test; nine delivered consistent results on stainless. We widened the search to Mangystau and Aktobe and ran a second round. Had the contractor ordered "just welders", it would have received a crew unfit for a third of the scope — and found out on site. Time spent on the brief pays back many times over.
Documents, medicals, safety induction and travel run in parallel. For a rotation project that is a serious workload, and with a provider whose logistics are in place a crew of 30–50 is usually mobilised in two to four weeks. It can be faster if the agency has a bench — welders just back from another project who have already passed the same client's test.
Don't forget crew composition. A welder without a pipe fitter, a grinder and a helper works slower and makes more mistakes, because time goes into bevel prep and fit-up. Ordering "welders only" is a common error; it is better to plan in units, for example welder plus fitter plus a helper shared between two stations. Some of these roles — fitters, erectors, helpers — we also fill through our open construction vacancies, where applications keep coming in.
Money, timelines and rotation: what drives the price
The cost of welder outsourcing has three layers. The first is the specialist's pay. The market is high: open listings on hh.kz offer even factory welders 500,000–600,000 tenge net, and a qualified pipe welder on rotation in oil and gas costs noticeably more — we broke down the ranges by grade in our article on welder pay on rotation. The second layer is the employer's taxes and mandatory contributions, which the provider carries. The third is the provider's fee and direct costs: recruitment, testing, medicals, travel, accommodation and PPE, if these are not on you.
When welder outsourcing is costed honestly, it should be compared not with a permanent employee's rate but with the full cost of in-house hiring: weeks of HR time, advertising, tests, medicals, safety training and, above all, people who stay on payroll between projects or have to be made redundant by the book. For a company with steady workload an in-house crew is almost always cheaper. For a contractor with three sites today and one in six months, provided personnel turn fixed costs into variable ones — that is the real economic value.
For foreign contractors, including Chinese ones, there is one more argument. Hiring local welders through a Kazakh provider is the fastest way to meet local-content requirements for staff without registering dozens of employment contracts on your own entity in the first months in the country.
Rotation needs its own agreement. Under Article 135 of the Labour Code a rotation shift may not exceed 15 calendar days, or 30 with the worker's consent, with summarised working-time accounting. In practice 15/15, 28/28 or 30/30 rosters need a back-to-back crew: if you need twenty stations working every day, you need around forty people in rotation. It is the first thing missed in budgets that count stations rather than people.
And one more cost line rarely planned for: replacements. Even a good crew loses people — someone fails the client's site test, someone has family issues, someone leaves for a competitor over a 50,000-tenge raise. The contract should state how many days the provider has to supply a replacement and who pays for mobilising them.
The pitfalls nobody mentions at the negotiating table
The first and most painful is rework. Under outstaffing, responsibility for weld quality sits with whoever runs the work — that is, you. The provider can guarantee the person passed the test, but not that they will weld the same way at height, in the wind, on a night shift. So agree a procedure up front: if a welder's repair rate exceeds an agreed threshold over two weeks, the provider replaces them free of charge.
The second is qualifications that "almost fit". A certificate to one standard when the client wants another; approval for one material group when the job is in another. Foreign certificates, including Russian NAKS certificates, are not accepted everywhere or automatically — it depends on the specific client, and the question must be asked before mobilisation, not at the gate.
The third is the legal limits of outstaffing itself. Article 137-1 of the Labour Code forbids using provided personnel to replace striking workers, during downtime or bankruptcy procedures, or when the host has introduced part-time working to protect its own staff. Sending people to harmful or hazardous work requires certification of the workplaces and informing workers of the results. Provided workers also count towards the host's average headcount, which affects the local-to-foreign staff ratio and work-permit calculations.
The fourth is cheap providers. If the rate is well below market, the money has come out of one of the three layers: people are underpaid and will leave within a month, taxes are not paid and the tax authority's questions will reach you too, or testing is skipped and you will learn about it from the QC log. This is exactly where employers often go wrong — comparing mark-ups without asking what the price includes.
Finally, the human factor. A welder is a scarce specialist and knows it. Provided people who feel like guests on site — worse accommodation, separate canteen, no productivity bonus — are the first to leave. The most stable crews we have seen were on projects where the client required the provider to offer the same living conditions and bonuses as permanent staff: more expensive at the start, cheaper over the distance. Welding rarely forgives savings, in metal or in people.
FAQ
Is welder outsourcing legal in Kazakhstan?
Yes. A works contract for welding is an ordinary civil-law transaction, and provision of personnel has been regulated directly since 2021 by Article 687-1 of the Civil Code and Article 137-1 of the Labour Code. What matters is that the contract reflects the real model: if you actually direct the welders' work, it is provision of personnel with all its legal limits, whatever the document is called.
How long does it take to assemble a welding crew?
A crew of 30–50 people, including test welds, medicals and logistics, is usually mobilised in two to four weeks. Narrow qualifications — stainless, alloy steels, work to ASME or API under a foreign client's inspection — can take longer, so it is best to submit the request right after signing the contract, not a week before start.
Who is responsible for weld quality under outstaffing?
Whoever organises the work on site — the host, with its procedures, supervisors and QC. The provider answers for the person matching the stated qualification, passing the agreed tests and being replaced quickly. That is why the acceptable repair rate and replacement procedure should be written into the contract.
Can I outstaff only some of my welders and keep the rest on payroll?
Yes, and it is a common setup: the core — permanent welders and the supervisor — stays in-house, while peak demand is covered by provided personnel. Just keep equal pay for equal work and remember that provided workers count towards your average headcount.